A1-A2 Newry Southern Relief Road / Bypass

 

Status
Construction scheme (future)
Where
To connect the A1 Newry Bypass directly to the A2 Warrenpoint Road, around the south side of the city
Total Length
Approx 1.5 miles / 2.4km depending on route chosen
Dates

Included in draft "Banbridge Newry & Mourne Area Plan 2015" - August 2006

Feasibility study published - August 2009

Scheme moved to forward planning schedule - 28 Nov 2014
Consultant appointed to produce Stage 1 Report - March 2015
Statutory Orders to be published (presumably in draft form) - 2019 (as of Jan 2017)

Cost

£100m to £211m depending on route chosen

(See note on costs below).

Photos
None as yet - please contact me if you have any to contribute.
See Also

General area map - Google Maps

A1 Newry Bypass scheme - on this site

A2 Warrenpoint Road - on this site

Banbridge Newry & Mourne Area Plan 2015 - Planning Service

Click here to jump straight down to updates for this scheme.

The arterial A1 runs around the western side of Newry city and, as of 2009, is being upgraded to dual-carriageway. Another dual-carriageway, the A2 Warrenpoint Road, runs east to Warrenpoint harbour from Newry. However, despite being only a mile apart, on opposite banks of the river, the only way to go between them is to drive right into the centre of the city. Local politicians have long called for a southern relief road to link them up, and this proposal was included in the draft "Banbridge Newry & Mourne Area Plan 2015" published in August 2006, along with a suggested route corridor. A feasibility study was published in August 2009 which found that the road should be built, but also noted the proposed route was not an efficient or easy one and suggested three other routes which were both cheaper and easier to build. A more detailed assessment process is underway (as of June 2015).

Route

No route has yet been chosen. However, the Feasibility Report published in August 2009 identified four possible route corridors which are shown shaded on the map below. The first of these, the blue one, is the original corridor proposed in the Banbridge, Newry and Mourne Area Plan in 2006. The other three are the alternatives proposed for the first time in the 2009 Feasibility Report.


View A1-A2 Newry Southern Relief Road in a larger map.

The 2009 Feasibility Report did not carry out an extensive study into these routes, but did note that the original "blue" route proposed "includes some significant challenges, including proximity to the existing Dromalane Quarry and the provision of suitable access arrangements onto the A1...". They proposed three further routes:

  • The Greenbank Corridor, shown in red on the map above, which runs from either the Ellisholding Road junction on the A1 or the Cloghogue junction on the A1 and runs north east to the existing roundabout on the A2 quite close to the city centre.
  • The Low-Medium Level Corridor, shown in green on the map above, which runs from Ellisholding Road junction on the A1 south-east across a low-level bridge to the A2 Warrenpoint Road.
  • The High Level Corridor, shown in grey on the map above, which is similar to the Low-Medium Level Corridor except that the bridge is higher above water level and swings inland to return to ground level.

All three of these options would require the addition of south-facing sliproads at the existing Ellisholding Road grade separated junction on the A1.

Note on Costs

The cost of the scheme will depend on the option chosen, something which as of Sep 2009 has not been decided. The indicative costs of these four options were reported in 2009 to be:

  • 2006 Area Plan Corridor - £178-£186m
  • Greenbank Corridor - £104m-£124m
  • Low-Medium Level Corridor - £100m-£132m
  • High Level Corridor - £211m

The cheapest of these is obviously either the Greenbank or Low-Medium Level Corridor.

Updates

28 Jan 2017: In a press release issued on 16 January, the outgoing DFI Minister stressed his committment to this scheme. The nearby Narrow Water Bridge scheme is a particularly prominent scheme, and was listed in the 2009 "Fresh Start" Agreement, but it has ovbious overlaps with this scheme since both involve bridging the Newry river, albeit at different points. So it seems that the two schemes are being considered as a pair, and could even end up beign combined. For now, however, they are separate schemes. The Minister said he "has instructed officials to take forward planning and development work on the Newry Southern Relief Road to allow the introduction of the Statutory Orders by 2019". Now, the scheme had already been moved to the forward planning shcedule in November 2014, but the target date of 2019 for Statutory Orders is new. The "Statutory Orders" are initially published in draft form and are usually subject to a public inquiry. Once it has passed the Inquiry (assuming it does) and is likely to get funding, the orders are then made properly. It's unclear from the press release which is meant, but realistically it is more likely to be the former. So by that reckoning we could expect a final route to have been announced by 2019 with a public inquiry likely to follow sometime after that. The Achilles Heel of this project is its huge unit cost, which is a consequence of the very difficult terrain. Even the cheapest option is over £100m which is very high for a road that would only be 1.5 miles long. By comparison, the 4 mile A31 Magherafelt Bypass cost only £45m. The cost/benefit analysis for the Newry Southern Relief Road will thus be quite challenging. The DFI would need to get the cost of the scheme down as low as possible, which would mean a low-level bridge over the Newry river.

3 May 2015: According to the minutes of a TransportNI Board meeting held on 28 November 2014, but just published, this scheme has been moved to the Forward Planning Schedule (and indeed it duly appears in the FPS list). The significance of this change is that schemes in the FPS are being actively planned, whereas before now the scheme was merely a suggestion, the only work being a feasibility study completed in 2009. Now that it is in the FPS it means that the planners will look at it in more detail. This does not in itself guarantee that it will be built, but it does mean that it has entered a more formal phase of planning. So the DRD have now said that a "Stage 1 Preliminary Options Scheme Assessment" has begun. This normally results in a range of options with cost estimates and a cost/benefit analysis of each one. There is no indication of when this might be published, but it could take a couple of years depending on the resources allocated to the task.

23 Nov 2014: Supporters of the nearby Narrow Water Bridge proposal have set up a web site here and their aim appears to be to continue to lobby for the provision of the bridge, whose construction fell through this time last year due to inaccurate cost estimates. The text on the main page implies that they are suggesting that that scheme be combined with the Southern Relief Road. The idea may be that the Southern Relief Road could start on the A1 further south than currently planned, close to the RoI border, and then cross the Newry River at Narrow Water via the proposed Narrow Water Bridge. This would require a short stretch of the road to be located in County Louth, so it would introduce a cross-border element. The expense of this scheme as it currently stands (anywhere from £100m-£211m) means that it is a low priority for the DRD, but this idea of linking it to Narrow Water and using a more southerly approach route is certainly worth looking into since it would require only one bridge to be built to achieve the aims of both proposals. With thanks to Paul Sloan for letting me know about the new web site.

22 April 2012: The Minister was asked about progress on this scheme via three Questions for Written Answer in the Assembly two weeks ago. He said that Roads Service are currently "undertaking further environmental and engineering assessments" and that this work will be completed in mid/late 2012. He added that this would inform the selection of the preferred route, but it sounds as if this could be after the date mentioned. He confirmed that so far Roads Service have spent just under £930,000 on planning for this scheme. However, he also stressed that the scheme has not, and never has been, given a definite go ahead, and that therefore there is no timescale for construction.

26 Sep 2009: The Feasibility Report into the scheme was published in August 2009, and a press release issued five days ago. The report showed significant benefits to proceeding with the scheme and proposed four alternative route corridors. The report however recommended against the route proposed in 2006, for cost and engineering reasons, instead suggesting three alternatives as shown on the map above. The cost estimates vary widely from £100m to £211m depending on the option chosen. On the basis of the report the Regional Development Minister has "asked Roads Service to proceed with further environmental and engineering assessments and to engage in a wider consultation process, considered necessary to identify a preferred corridor for the Newry Southern Relief Road." There are still no firm plans to proceed with the scheme which, if it does happen, is unlikely to happen in the near future and perhaps not for ten years. It is also interesting to note that the feasibility report comments that constructing this scheme, at least if the Low-Medium Level Corridor is chosen, could render the proposed Narrow Water Bridge project redundant.

23 May 2009: According to the Minister of Regional Development (during a question and answer session in Stormont a couple of weeks ago) the feasibility study into the Newry Southern Relief Road has now been completed, but Roads Service want to do additional work "developing its findings" before releasing it publicly. He said "The project is important. Roads Service and the consultants it has engaged have undertaken significant assessment work." and "We hope to be in a position to present the reportís findings soon". The first of these comments suggests that the feasibility study was favourable towards the road's construction, but we shall have to wait and see.