Status
|
Construction scheme
(future) |
Where
|
To
construct a new dual-carriageway to
connect the upgraded A5 in Strabane to
the N14 route to Letterkenny in county
Donegal. |
Total
Length
|
0.5 km / 0.3 miles
(Of which 79 metres is in Northern
Ireland)
|
Dates
|
Public exhibition held
- Apr/May 2011
Direction Order
published - 19 July 2011
Planning permission
granted in Rep of Ireland - 30 May 2012
Construction had been due to begin
2012/13 (as
of 2011)
|
Cost
|
£unknown
Likely to be funded by Republic of
Ireland |
Photos
|
None as yet -
please contact me if you have any to
contribute. |
See
Also
|
N14
Letterkenny to Lifford dualling -
on this site
A5
dualling Derry to Aughnacloy - on
this site
General
area map - Google Maps
|
Click
here to jump straight down to updates
for this scheme.
This project, which is being managed by Donegal
County Council, took its original form around
2007, with a plan
was to upgrade the N14 road which connects
Letterkenny in county Donegal to Northern
Ireland and hence on to Dublin via Strabane. The
N14 plan officially ends at a roundabout south
of Lifford, where this little scheme takes over,
connecting it to the future A5 in Northern
Ireland. While a short distance, a bridge over
the River Finn will be required to carry the new
road. Donegal County Council call this a
"significant structure between 100 and 300
metres in length". Assuming the A5 project is
completed as planned past Strabane, only the
last 79 metres of the road would be in Northern
Ireland.
Progress
28 Oct 2024: It is now over eight years
since I updated this page, and pretty much
nothing has happened. Following delays to the A5
project, DFI Roads now plans to proceed
initially ONLY with the upgrade of the A5
from south of Strabane to Ballygawley, but not
including a new Strabane Bypass to which this
link road would connect. So for now it is on the
drawing board. Similarly, plans are progressing
for the N14
Letterkenny to Lifford scheme in Donegal
which, if built before the A5, will have to
terminate on the west bank of the Foyle south of
Lifford. Currently work on the the N14 scheme
could commence in 2028. So this update is really
just to report that there is nothing to
report...
2 May 2016: Three and a half years on
since the last update, and I felt it was worth
giving some kind of update. In late 2012 it
looked as if there was imminent movement on this
scheme, but the legal challenge resulted in
nothing happening. Now it seems that the scheme
is still a live scheme in the Republic of
Ireland - the
page on the Transport Infrastructure
Ireland web site (TII, which replaced the NRA in
August 2015) gives the status as "in planning"
with a note that "its progression is now
subject to the timing of the Northern Ireland
Roads Service (sic) A5 (WTC) project
advancing to construction". It also states
that the scheme was given planning approval by
An Bord Pleanála on 30 May 2012. The
larger-scale N14
Manorcunningham to Lifford upgrade - which
was suspended in 2010 giving rise to the need
for this much shorter link road - is still
officially "suspended". So the position seems to
be that this scheme will happen once the
adjacent section of the A5 south of Strabane is
completed. Since this does not look likely to
happen until at least 2021-2023, I think we are
still a good few years off construction. If the
financial situation in the Republic of Ireland
improves it is even possible that the
'suspended' N14 upgrade might take place before
the A5 south of Strabane gets upgraded.
12 Sep 2012: Something is definitely
going on behind the scenes about this link road
and bridge, and I suspect there may be some kind
of announcement about this link road in the
not-too-distant future. Firstly, a reminder of
the background. Since this scheme is designed to
link only into the new A5 at the
Strabane end, there is no point building it if
the new A5 is not being provided at the far end.
Back in February the "Roads" Minister announced
that he would be initially proceeding with two
stretches of the A5 (Newbuildings to North of
Strabane; south of Omagh to Ballygawley).
Neither of these included the stretch that this
link road will link into. Therefore we have
assumed that this scheme will not be going ahead
in the near future. Now, two things have
recently appeared on an Irish government web
site. Firstly this
tender for legal services for the N56 "and
N14/N15 to A5 Link Road" was awarded to VM
McMullin Solicitors of Balybofey on 25 May 2011,
but only just published online. But secondly this
tender appears to be for futher legal services
for land acquisition for the "N14/N15 to A5
Link" only, and was put out to tender on 5
September 2012, with a closing date of 28
September 2012. Why the sudden flurry of
interest in acquiring the land for this scheme?
(with many thanks to Cormac Ó Murchú for finding
these.) Meanwhile, the notes
on a DRD meeting held on 3rd September contain
the following comment: "ensure the Minister
was kept informed of developments regarding the
bridge at Strabane and that alternate
options were being considered for the
associated finance" (emphasis mine). This
must surely refer to the N14/N15 to A5 link
road, and implies that somehow additional
funding has become available by some means to
allow its construction. However, this raises
another question: Since the link road can't go
ahead without the adjacent section of A5, does
this mean that a bit more of the A5 is going to
be built than previously announced? We will have
to wait and see.
9 Nov 2011:
The Irish government's decision not to provide
£400m for the A5
upgrade until at least 2016 means that
this scheme, too, is now on hold. Since it would
connect to the upgraded A5, the scheme would
serve no purpose without it. Therefore, this
scheme is now on the long finger.
8 Oct 2011:
It now seems certain that Roads Service and the
NRA (in the Republic of Ireland) do indeed plan
to press ahead with this scheme at the same time
as the main A5 scheme. This was evidenced by the
publication of the Direction
Order in July 2011. A Direction Order
(used in Northern Ireland only) is the legal
document that is required to give Roads Service
permission to build a new trunk road. It is
unclear whether this short link road was
included in the A5 Public Inquiry, but since the
section inside Northern Ireland is only 79
metres long it would seem wasteful to hold an
entirely separate public inquiry for it!
5 June 2011: Further to my
previous update, Donegal County Council have now
put a PDF
of their proposals online. This shows that
the link road will consist of a fairly
substantial eight span bridge, three of which
appear to be arch spans with five beam spans.
Most of the bridge traverses the flood plain, as
the River Finn itself is not massive. The PDF
gives the dates of the environmental impact
statement and compulsory purchase order (similar
to a Northern Ireland vesting order) as "summer
2011" with construction to take place "2012
onwards". This way this latter date is phrased
seems to imply that it will be built
concurrently with the construction of the A5
dual-carriageway in Northern Ireland which is
also to be built from "2012 onwards". With
thanks to Cormac Ó Murchú.
14 May 2011: Donegal County
Council have now held a public
exhibition of their preferred route (held
mid April until 8 May 2011). Unfortunately I
can't seem to locate any copies of the proposals
online. The official
web site for the scheme on the Donegal
CoCo web site also says that "the
Environmental Impact Statement/ Environmental
Statement and Compulsory Purchase Order are
expected to be ready for publication by end
May 2011." No details of a possible
construction date are mentioned.
31 Oct 2010: The financial
chaos in the Republic of Ireland has resulted in
the plan to upgrade
the N14 from Strabane to Letterkenny being
"suspended" as of two weeks ago. However,
Donegal County Council have now split the
Strabane-Lifford link road from this larger
scheme and are taking it forward independently
because this section is required to link into
the proposed A5 dual-carriageway from Derry to
Aughnacloy which is being part funded by the
Republic of Ireland. As of two weeks ago the
latest information was that "Roughan &
O’Donovan Consulting Engineers have now been
appointed to complete the Design and the
Environmental Impact Assessment/Environmental
Assessment Report Statutory Processess for the
project. It is likely that some amendments
will be necessary to the design for the N14
Letterkenny to Lifford/Stabane Scheme and the
N15 Lifford to Stranorlar scheme to
incorporate the layout of the N14/N15 to A5
Link." With thanks to Cormac O Murchú for
letting me know about these changes.
23 Mar 2008:
Construction of the scheme had been due
to get underway in mid 2008. However, according
to the Roads Service report to Strabane
Borough Council in Autumn 2007, the scheme
is now being reviewed by the authorities both
North and South. This is because the scheme is
due to tie in to the A5 Strabane Bypass.
However, as of summer 2007 a plan is being
progressed to upgrade the A5 to dual-carriageway
and this will affect the design of the
Strabane-Lifford link. Therefore construction is
likely to be delayed. Donegal Council Council's
web site is now giving a start date of "2013",
considerably later than previously believed.
|