Status
|
Construction scheme
(current) |
Contractor
|
John Graham
Construction Ltd
|
Where
|
To
convert the citybound hard shoulders
into peak-period bus lanes on:
M1 from Sprucefield (junction 7) to the
existing bus lane at Ballyskeagh
(between junctions 2 and 6) with a later
extension from junction 8 to junction 7.
M2 from Greencastle (junction 2) to
Duncrue Street (junction 1B) with bus
gates at j1 and j1B.
|
Total
Length
|
6.0 miles / 9.7 km
(3.5 miles / 5.6 km on M1, 2.5 miles /
3.2 km on M2)
|
Dates
|
1999 - M1 bus lane
opened Stockman's Lane (j2) to Broadway
(j1)
22 Aug 2006 - M1 bus
lane opened Ballyskeagh to Blacks Road
(j3)
19 Nov 2007 - M2 bus
lane opened on approach to Sandyknowes
(j4)
8 Nov 2016 - this scheme put out to
tender
Early 2017 - work was expected to begin
but tender was not awarded (to last 5
months)
Jun 2017 - review of design and funding
underway. Construction uncertain.
9 Mar 2018 - scheme went out to tender
7 Jun 2018 - contract awarded to John
Graham Construction Ltd
Early August 2018 - work began
11 Mar 2019 - both bus lanes opened
10 Aug 2020 - extension of M1 bus lane
from Blaris (junction 8) to Sprucefield
(junction 7) opened
|
Cost
|
£5.6m whole scheme
cost - as of Aug 2020
£3.3m (for construction) - as of Mar
2018
(changed from £2.9m as of Nov
2016)
plus an additional £1.1m for the
extension to M1 junction 8 in 2020
|
See
Also
|
See below for maps
|
Click
here to jump straight down to updates
for this scheme.
Currently (as of June 2018) there are two
peak-period, hard shoulder bus lanes on
motorways in Northern Ireland. On the M1,
there is a bus lane running from Ballyskeagh
(between junctions 6 and 3, close to the River
Lagan) to the terminus of the M1 at Broadway
(with a short gap from Black's Road to
Stockman's Lane). On the M2, there is a
bus lane running from half way between
Templepatrick and Sandyknowes (junctions 5 and
4) to Sandyknowes roundabout. (When this was
introduced in 2007 it was to be a three year
temporary measure during the Westlink upgrade,
but in fact it was never removed.) There is
another short stretch running from Sandyknowes
roundabout to Hightown Road.
This scheme will see additional bus lanes built
on both motorways. On the M1, the busway
will be extended by approximately 5.6 km west
from Ballyskeagh all the way through junction 6
to junction 7 (Sprucefield) which is home to an
existing park-and-ride facility. There is an
intention to extend it further to junction 8
shortly afterwards. On the M2, a new
section of busway will be constructed from the
Greencastle junction (j2) to the offslip at
Duncrue Street (junction 1B), a distance of
approximately 3.2 km. There will thus be a gap
on the M2 hill section (Hightown Road to
Greencastle), which is likely because the hard
shoulder on this section is not continuous due
to restrictions at Bellevue Bridge and
Greencastle interchange that result from the
original 1960s design.
Both of the new M1 and M2 bus lanes will pass
through existing junctions (junctions 6 and 7 on
the M1 and junction 1 on the M1) - it is not yet
clear how this will be achieved. One possibility
is for buses to go up the offslip and back down
the onslip. The only place this would not work
is junction 7 on the M1 as there is no offslip
at this junction. The maps below show the
sections in question.
M1 BUS LANE
Purple shows
existing bus lanes, while red
shows the proposed new bus lanes, including the
planned extension from j7 to j8.
(note route through Saintfield Road and
Sprucefield interchanges is conjectural)
M2 BUS LANE
Purple shows
existing bus lanes, while red
shows the proposed new bus lanes.
(note route through Fortwilliam interchange is
conjectural)
The two busways will require engineering work
for two reasons. Firstly, historically hard
shoulders tended not to be built to as high a
standard as the main traffic lanes, and hence
may need lifted and rebuilt in order to
strengthem them. Secondly, the bus lanes will
require new road layouts in places, both
physically (kerbing) and in terms of lane
markings.
Updates
11 Sep 2020: In August an extension of
the M1 bus lane from Blaris (junction 8) to
Sprucefield (junction 7) opened
to traffic. This was a component of the
wider scheme, but undertaken at a later date.
The cost was given as £1.1m and work took place
between January and August 2020, also by Graham
Construction.
6 Mar 2019: According to DFI
Roads, the M1 and M2 bus lanes are now
complete and will become operational on 11
March. This was preceded in February by a new
Statutory Rule that made them legal bus
lanes. The most interesting part of the scheme
from the perspective of the travelling public is
the setup at Applegreen's Lisburn Services on
the M1, where the bus lane continues past both
the onslip and offslip. This will require
traffic entering and leaving Applegreen to cross
the bus lane via an uncontrolled crossover
manoeuvre. DFI have released leaflets (here
and here)
outlining how this will work. Although it's
certainly eyebrow-raising, the risk of a
collision is mitigated by the low frequency of
buses compared to general traffic, and the fact
that the buses are limited to 40mph in the bus
lane. Nevertheless, a bit of inattention on the
part of a driver could result in a side-swipe,
so take care. Work has taken just under 8 months
to complete, so well done to the contractor John
Graham Construction Ltd. DFI also noted in the
press release that 20% of people entering
Belfast on the M1 in the morning peak are on
buses.
3 Dec 2018: Work has been progressing
well on this scheme since the summer. Initial
work on the M1 focused on communications works
between Stockman's Lane (j2) and Broadway (j1),
and between Tullynacross Bridge to Blacks Road
(j3). Bus gates have also been constructed on
the M2 foreshore at Fortwilliam and Duncrue
Street offslips (j1 and j1B). Work in the latter
part of the priejct has focused on further
communications works on the M1 between
Tullynacross Bridge and Sprucefield (j7) and the
M2 from Ballyvesey Road (near Applegreen) to
Sandyknowes (j4) and from Greencastle (j2) to
Duncrue Street (j1B). Reconstruction work is
also necessary on the various stretches with the
white lining and new signage being erected last
of all. The scheme should be completed in
January. DFI have published an information
leaflet about the new bus lanes, which
includes diagrams of the new bus gates on the
M2. They've also put up a couple of photos of
construction underway here.
With thanks to John Quinn for much of this
information.
14 Jun 2018: The tender for this scheme
was awarded
last week to Graham Construction -
congratulations to them - although they also
appear to have been the only company that
submitted a tender. The tender value is
approximately £3.3m, which is lower than the
£3.9m estimated when it went out to tender, and
not much higher than the failed tender process
that paused the scheme back in 2016. I've marked
the scheme as "underway" now that the tender has
been awarded. There is no word on when
construction is actually likely to begin, but
the contractor is likely to want to take
advantage of the summer weather and so I would
expect to see work getting underway later in the
summer, perhaps after the July break.
22 Mar 2018: The scheme finally went
back out
to tender on 9 March, with a duration of
six months and an estimated construction value
of £3.9m, which is £1m higher than the value
quoted the last time the tender was issued in
2016. On that occasion the tenders received were
higher than expected and so a contractor was not
appointed. The scheme description this time
round doesn't really sound any different, so I'm
not sure what has changed to make it worth
re-issuing the tenders. In a presentation to Belfast
City Council in December a DFI employee
said that in reviewing they design they "had
considered the technology used in the smart
motorways across the UK" without
elaborating on what the means. Perhaps also -
based on the higher cost being quioted this time
- DFI have accepted the higher cost and
re-evaluated the budget to allocate more money
to the scheme. In any case, the overall lengths
of proposed bus lanes are unchanged. Tenders
like this normally take 3 to 5 months to be
awarded, so we could see construction getting
underway in the late summer or early autumn. The
scheme seems to be being regarded as part and
parcel of the York Street Interchange project,
with the idea being to provide alternative ways
to get into the city once that scheme gets
underway and York Street gets even more
congested than it is now.
30 Nov 2017: This scheme is not dead!
Having gone through procurement this time last
year, and then vanishing due to the tenders
being higher than expected, the scheme went back
to the design stage. It now appears that work
has actively taken place during the year because
DFI's October procurement
plan update shows it as a future tender
with an estimated date of award of March 2018
and an estimated construction cost of £3m.
However, it has yet to appear on DFI's list of current
tenders so it's possible this date may
slip a bit. It will be interesting to see what
changes have been incorporated into the design
to bring the cost down since there's little
scope for significant savings in a scheme like
this, short of reducing the lengths of the
proposed bus lanes.
10 Jul 2017: In the previous update in
April I noted that having been put out to
tender, this pair of schemes simply vanished. We
now know why. According to DFI
Roads' report to Lisburn and Castlereagh
Council three weeks ago the tenders received
were higher than anticipated and so the scheme
was pulled. The report says: "A procurement
process was completed in January 2017,
although the tendered costs were significantly
higher than expected and as a result the
contract was not awarded. Currently a review
of the procurement strategy and any
alternative delivery of the scheme is
underway, to determine if it can be procured
in a more cost effective way, or with reduced
requirements." In other words they're
looking for ways of either getting more money,
or reducing the design to save money. The
wording doesn't sound particularly enthusiastic
so it's possible we will hear nothing more of
this scheme for a while.
14 Apr 2017: Something strange has
happened to this scheme. It went out to tender
in November 2016, but over the past month or two
has completely vanished off the TransportNI procurement
web site. No tender seems to have been
awarded. This suggests that the scheme has got
pulled out of the schedule for some reason. One
possible reason is that York Street Interchange
now looks to be on the long finger, and
alleviating congestion during construction was
one of the reasons for the M2 works. However
that does not explain the M1 works and so there
is still a mystery around what has happened
here.
3 Dec 2016: The tender
for the two busways was advertised on 8 November
2016. This implies that one contractor will be
responsible for both schemes, and so work is
likely to take place concurrently on both. Work
is currently due to begin early in 2017. Work is
scheduled to take 5 months to complete. In a
Question for Written
Answer (AQW 612/16-21) the Minister said
that the M2 bus lane "would be a temporary
traffic management measure associated with the
proposed York Street Interchange scheme, to
help alleviate traffic congestion by
encouraging a modal shift to public transport
for travel into Belfast at peak times during
the 3 year construction period." Given
that the same thing was said when the M2 bus
lane was introduced at Sandyknowes in 2007, but
it is still there today, I think we can assume
that it the bus lane will be permanent despite
this statement!
|