Status
|
Construction scheme
(proposed) |
Contractor
|
Not yet appointed
|
Scheme
|
New
high-quality dual-carriageway bypassing
the Watedrside of Derry from the
existing terminus of the A6
dual-carriageway at Drumahoe to the A2 at
Gransha, and an upgrade of the existing
A2 dual-carriageway from Caw to Maydown.
|
Total
Length
|
5.3 km / 3.3 miles
|
Dates
|
Mar 2005 - Pilot study
to select route from Castledawson to
Derry announced.
Dec 2005 - Funding
announced to build section from Dungiven
to Derry.
Feb 2007 -
Preliminary route corridor selected.
May 2008 - Five route
options published.
6 May 2009 -
Preferred route announced.
14 Dec 2011 - Draft
legal documents published.
Jan 2012 - Public exhibitions.
24 Sep 2012 to 2 Oct
2012 - Public Inquiry held.
2012 - Large illegal dump discovered at
Mobuoy, on route of Phase 2
ca End Mar 2013 -
Inspector submitted Public Inquiry
report.
24 Feb 2016 -
Departmental Statement published.
6 Apr 2023 - Dungiven-Drumahoe
element of scheme opened (Phase 1)
2023 - Road has no funding and therefore
no current plans to open to tender.
Construction date unknown.
|
|
£200m for phase 2,
as of Oct 2021
|
Click here to jump
straight down to updates for this scheme.
This major project
was first announced on 13 December 2005 by the
Northern Ireland Secretary of State Peter Hain
as part of a larger investment package for the
city of Derry, and work got underway in 2018.
Due primarily to lack of cash, but also due to
the discovery of a large illegal dump at Mobuoy,
the scheme was split into two phases. Phase 1
was constructed between 2018 and 2023 and saw a
dual-carriageway bypass of Dungiven town and
dualling of the existing A6 from there to a
"temporary" terminus at Lismacarol at Drumahoe.
Phase 2 will extend this road cross-country past
Drumahoe to the A2 at Maydown on the
north-eastern periphery of Derry city. It will
also see a section of the existing A2 improved
from Maydown to Gransha. The new A6 road will be
build to a high quality with two lanes each way,
no breaks in the central barrier. There will be
no intermediate junctions between Lismacarol
roudnbout, which will be grade-separated, and
the terminal roundabout at Maydown.
Strip Junction Map
This is a strip map of the design that was
published in May 2009, and is still correct as
of 2024.
|
WEST
Begins on
A2 dual-carriageway, Derry
2+2 lanes
|
STRADREAGH
or GRANSHA
|
A2 Clooney
Road
(into Derry)
|
|
Local
access
A2
Clooney
Road
(to Limavady)
|
|
5.3 km
/ 3.3 miles - 2+2 lanes
|
LISMACAROL
ROUNDABOUT
(DRUMAHOE)
|
A?
Glenshane
Road
(existing A6)
(into Derry).
|
|
Tirbracken
Road
|
|
EAST
Ends on A6
dual-carriageway, Dungiven
2+2 lanes
|
Updates
22 Mar 2024: DFI recently released
the "first day briefing" given to the new DFI
Minister from last month. Concerning this
scheme, the DFI's brief to the Minister was that
DFI has "been liaising closely with DAERA in
relation to this project to ensure that any
remediation proposals take account of each
parties’ requirements, including those
associated with Phase 2". As the route of
the planned road traverses the Mobuoy site in a
shallow cutting this presumably means that DFI
want to ensure that, if the material is left in
situ, it will be possible to build the road over
it as planned. However, the DFI position is that
"construction of phase 2 will not commence
until the remediation of the Mobuoy waste
site has been completed by DAERA". Since
this still looks to be years away, this
reinforces my conviction that this scheme will
not be progressing in the next number of years.
21 Feb 2024: The new DFI Minister John
O'Dowd was asked about the scheme in a Written
Answer in the Assembly recently (AQW
5524/22-27). In his answer, the Minister
explicitly linked the lack of a timescale on the
illegal Mobuoy dump site: "Once plans for
remediation of that [Mobuoy] site are in
place, a delivery strategy for Phase 2
including timelines will be finalised".
That implies the scheme won't happen until
Mobuoy is rectified, and to be honest that doesn't
seem likely to happen even in the next
decade. Additionally, this section is likely to
have a poor business case when treated
separately from the scheme that has now been
built. The longer the delay goes on the greater
the chances that the scheme would have to go
through another public inquiry as a standalone
scheme. So I continue to be of the view that
this scheme may not happen at all, certainly not
in the next ten years.
19 Jul 2023: I have now created this
page by splitting it off from the main A6
Derry-Dungiven page as Phase 1 of the scheme is
now complete. Phase 2 is planned to extend the
road from Drumahoe to Gransha. Although much
shorter than Phase 1 at 5.3 km, due to some very
challenging terrain, high land costs and a major
bridge over the river Faughan, it has almost the
same cost (£200m) as Phase 1. This is the main
reason it did not happen at the same time as
Phase 1 (2018-23). However, a second factor is
the illegal dump at Mobuoy which was discovered
eleven years ago and which lies directly on the
route of Phase 2. Proceeding with the road would
require a permanent solution to the Mobuoy dump
issue, and that does not
seem imminent. The alternative, re-routing
the road around the site, is undesirable for DFI
as it would likely trigger a second public
inquiry during which the road would need to be
re-assessed on a stand-alone basis. Given that
it was taken through the inquiry along with
Phase 1 last time (2012) its economic case
looked much better than it would if taken
forward separately. My feeling is that this
scheme is unlikely to proceed in the next 5-10
years, because there are a large number of other
schemes, such as the A5 dualling project, that
are a higher priority. The longer the delay goes
on the greater the chances that the scheme would
have to go through another public inquiry, and
for this reason it is possible it may never
happen at all.
Updates prior to this point were made on the
page for Phase 1, which you can
find here.
|