Status
|
Construction scheme
(future)
Contractor: BAM,
Balfour Beatty, FP McCann, ARUP, Atkins
|
Where
|
To
upgrade the A5 by building a new high
quality dual-carriageway from
Newbuildings (south of Derry) to just
north of Strabane. |
Total
Length
|
14.3 km / 8.9 miles
|
Dates
|
For background to
scheme see
the page on the whole A5 project.
17 July 2007 - Executive decides to
proceed with plan
21 July 2009 - Preferred route announced
May, June 2011 - Public Inquiries held
9 Nov 2011 - Irish government postpones
financial contribution
14 Feb 2012 - This section broken off as
a separate scheme
31 July 2012 - Scheme passes public
inquiry and is approved
Sep 2012 - Work due
to begin but halted due to legal
challenge
Autumn 2016 - New
public inquiry (for entire A5 scheme)
Oct 2024 - This element removed from the
construction schedule
|
Cost
|
£207m (as of Dec
2019)
(changed from £150m as of Oct
2016; £170m as of Feb 2012)
Price is more likely to be closer to
£300m as of Feb 2024, but this is not
official.
|
See
Also
|
General
area map - Google Maps
Whole A5
scheme - on this site
Official
web site on whole A5 scheme
|
Click here to jump straight
down to updates for this scheme.
This page is specifically to follow the
construction of the A5 from Londonderry
(Newbuildings) to Strabane. A separate page
is dedicated to following the entire A5 scheme
through the planning and funding process.
This scheme is part of the ambitious plan to
upgrade the entire 88km A5 to high quality
dual-carriageway standard from Newbuildings
(just south of Derry) to Aughnacloy. See here for
details and history. In February 2012, in a
climate of reduced finance, it was decided to
break the scheme into a number of phases and
build them over a period of years. This scheme
represents about 2/3 of what was originally
"Section 1", ie the section from Newbuildings to
the south side of Strabane. It will follow the
same design as "Section 1", except that it will
omit the 7.3km Strabane Bypass stretch, ie it
will stop north of Strabane.
Most of the road will be built to dual-carriageway
standard with two lanes each way, no side accesses
and no hard shoulders. The technical term for this
standard is "Category 6". The northernmost 1.3 km
will be built to single-carriageway standard with
one lane each way. There will be no intermediate
junctions on the dual-carriageway stretch. The
strip map below shows the design of the road.
Junction Strip Map
Dotted lines show the planned future extension
southwards.
|
NORTH
Begins as
A5 Victoria Road, Newbuildings
(approx 2
miles / 4 km south of Londonderry)
|
Junction
1:
Newbuildings North
|
|
|
B?? Victoria Road
(current A5)
|
|
1
lane each way – 1.3 km / 0.8
miles
|
Junction
2:
Newbuildings South |
.
|
|
Link road to B??
(current A5)
|
|
13.0 km / 8.1 miles
|
Junction
3:
Ballymagorry
(Strabane north)
|
|
|
B?? (current A5)
B49 Berryhill
Road
Victoria Rd (current A5)
into Strabane
|
|
SOUTH
Terminates
on existing A5 north of Strabane
|
The route itself follows the existing A5, but
crosses from west to east several times. You can
see the design as proposed here.
This is not the first time an upgrade on this
route has been proposed. A plan to upgrade the
existing A5 here to 2+1 standard was briefly
proposed between July 2006 and July 2007. See here.
Updates
9 Oct 2024: I am now retiring this page,
as it is no longer relevant - DFI have now
removed this element of the project from the
schedule, and replaced it with a new plan to
build the stretfch from Newbuildings to SOUTH of
Strabane later on this decade, perhaps
commencing in 2028.
21 Feb 2024: I am bringing this page
back out of hibernation after six years after
yesterday's news that the scheme now has
sufficient funding to begin - bar any further
delays - later this year. If you want the
details on the A5 scheme generally, see the general A5 page.
This part of the project is scheduled to be the
first to be built. It is entirely offline so
should not impact much on traffic during the
construction period, which will probably last
about three years. It is also relatively simple
as there are no junctions between the roundabout
south of Newbuildings and the temporary terminus
north of Strabane. It will simply be 13 km of
new dual carriageway, plus another 1.3 km of
single carriageway to bypass Newbuildings
itself.
24 May 2018: This page exists
specifically (perhaps optimistically!) to follow
the construction of the A5 from
Londonderry (Newbuildings) to Strabane. A separate
and much fuller page is dedicated to
following the entire A5 scheme through the
planning and funding process. This is just to
note that construction has once again been held
up by a legal challenge and, as discussed in
more detail on the main A5 page, it now seems
that 2019 is the earliest possible start date
for this stretch. That would see completion
around 2021/22. Until work begins, this page
will remain dormant.
11 Apr 2016: This page exists
specifically to follow the construction
of the A5 from Londonderry (Newbuildings) to
Strabane. A separate
and much fuller page is dedicated to
following the entire A5 scheme through the
planning and funding process. Subject to the
public inquiry that is due to take place this
autumn, work on this stretch of the A5 is due to
get underway during 2017, ie within the next two
years. The DRD have now revealed their updated
plan for the stretch (go to
this page, and clicking on the + sign
beside "Brochures" at the bottom and click the
Brochure for Section 1). It shows a number of
minor changes over the 2012 design, but a
slightly more significant change to the design
of Junction 3, the one north of Strabane. It's
simpler to just show you (below), but you can
see a third new roundabout has been added, plus
other realignments. North is to the left,
Stabane is to the right.
Secondly, Junction 3 is also going to be the
temporary terminus of this stretch, with the
extension past Strabane following later. I
have been wondering exactly how the junction
will look during the period when it is a
temporary terminus, and TransportNI have now
ended the suspense and revealed how it will
look:
DRD map showing how A5 junction 3 (Strabane
North) will look upon completion of the
Newbuildings to North of Strabane stretch,
but before construction of the next stretch
south past Strabane. [DRD]
So they are basically going to build the two
north-facing sliproads, the bridge and even a
section of the future A5, but divert all
traffic up the sliproads for the few years
until the rest of the A5 is built. This is the
most cost-efficient way to do it, as it
minimises future junction restructuring, but
is also uncomfortably reminiscent of this
junction on the M2 Ballymena Bypass
which was a "temporary" terminus from 1969
until 2010. Let's hope the same thing doesn't
happen to this junction in Strabane! On the
other hand, what would we road enthusiasts
talk about if it were not for oddities such as
temporary terminii?? So hurrah for a new
temporary terminus!
18 Nov 2015: To clarify, this page
exists specifically to follow the construction
of the A5 from Londonderry (Newbuildings) to
Strabane. A separate
and much fuller page is dedicated to
following the entire A5 scheme through the
planning and funding process. It has been over
three years since the last update, because a
legal challenge meant that commencement did not
take place as anticipated in September 2012. We
are now part way through a new planning process,
and the public inquiry will probably take place
early in 2016. The same contractor, however,
remains in place and can start very quickly
following the (hopefully successful) outcome of
the public inquiry. The reason for this update
is to note that funding now appears to be in
place in the form of £75m from the Irish
government, and a very strong commitment from
the Executive to provide the additional
estimated £95m to get this stretch underway. So
I'm now as certain as it's possible to be in the
world of politics that construction on this
stretch will get underway sometime in 2017.
31 Jul 2012: Today the scheme was approved
by the DRD Minister, having passed the Public
Inquiry. Work is now due to begin "in the
Autumn", probably September or October, so we
are probably within 3 months of commencement.
There is still no information about how the
south (Strabane) end of this scheme will end, ie
what we call "Junction 3" in the strip map
above. This will hopefully be revealed in due
course, as a decision must have either been
taken already, or will have to be taken soon.
15 Feb 2012: This
scheme came into existence yesterday, following
a major funding announcement.
The Public Inquiry process is not yet concluded,
but the Minister estimates that work could begin
in September or October 2012 if it passes this
hurdle. Construction is likely to take between 2
and 3 years. The total cost of £170m is an
estimate, and may change as the scheme proceeds.
|