Status
|
Construction scheme
(under construction) |
Where
|
To
carry out a series of three schemes to
widen the A4 through Enniskillen to two
lanes each way. |
Total
Length
|
0.5 km / 0.3 miles
|
Dates
|
Enniskillen
Throughpass originally built - 1986
Wellington Road
Improvement Strategy developed by 2010
Widening of Wellington
Road around Eden Street - 2010
Phase 1 given go-ahead - early 2015
Phase 1 public consultation held - Nov
2015 to Jan 2016
Phase 2 and Phase 3 still at planning
stage (as of Apr 2016)
Phase 1 to begin 24
Oct 2016 and be completed by end March
2017
Construction of Phase 1 to last 16 weeks
(as of Jan 2016)
|
Cost
|
Phase 1 - £500,000
(for construction; land additional) - as
of Oct 2016
Phase 2 - unknown
Phase 3 - £3m - as of Aug 2015
|
Photos/Maps
|
None as yet
|
See
Also
|
A4
Enniskillen Southern Bypass - on
this site
|
Click here to
jump straight down to updates for this
scheme.
The east-west A4 passes straight through
Enniskillen. Formerly following the main street,
the A4 was later diverted onto the Enniskillen
Throughpass which was completed in 1986. The
road today carries substantial amounts of
traffic and is regularly congested through the
town. This scheme consists of a series of three
proposed phases which will increase capacity by
easing key bottlenecks. The DRD seem to regard
the three schemes as part of a longer-term "Wellington
Road Improvement Strategy". This strategy
seems to have included past schemes such as a
traffic management system installed at the
western end circa 2011, and widening work on the
Throughpass in 2010. This page, however,
concentrates on the three proposals yet to go
ahead as of 2016:
- Widening a 300m stretch of the A4 Dublin
Road to provide two lanes eastbound from the Tempo
Road junction at the Fire Station, past
the A32 Wickham Place junction (around Tesco
and the Belmore Court Hotel) and ending close
to the start of the 40mph speed limit,
where presumably the two lanes will merge into
one.
- Upgrade of the Gaol
Square signalised junction to permit two
lanes to turn right from Wellington Road (the
Throughpass) onto the Dublin Road, instead of
the single right-turn lane that currently
exists. This will probably be accomplised
within the existing road footprint by
rebuilding the traffic islands and adjusting
the traffic signals.
- To widen a 200m stretch of the Wellington
Road from one to two lanes eastbound from the
Erneside
footbridge (where the current two lanes
drop to one) to the
end of the Inis Ceithleann Bridge, where
it currently becomes two lanes once again.
Upon completion, the Throughpass will have two
lanes in each direction for its entire length,
increasing capacity. The only unknown is the
related A4 Enniskillen Bypass project which
would, upon completion, significantly relieve
the Throughpass. It, however, is on a much
longer timescale, so TransportNI may still
progress this scheme in order to provide shorter
term benefits. I am grateful to the Impartial
Report for the invaluable information in this
news story about the scheme from last
August.
Updates
19 Jul 2023: This update is just to say
that, six years after the completion of phase 1
of this plan, nothing further appears to have
happened. Neither the upgrade of Gaol Square to
allow two right-turn lanes from the Throughpass
onto Dublin Road, nor the widening of the shaort
stretch of the Wellington Road that is still one
lane eastbound, has happened. While it is true
that the councils are currently working on local
transport strategies, these upgrades are on the
strategic A4 which means that they should still
be the responsibility of DFI Roads rather than
the councils. It is also possible that, with the
construction of the A4 Enniskillen Bypass
planned for the next few years, DFI might regard
improvements to Wellington Road as no longer a
good use of money. It would be worth a public
representative asking DFI about the current
status of these proposals.
23 Oct 2016: Work on Phase 1 of
this scheme is due
to begin tomorrow, 24 October and last
until 27 November. This will see 100 metres of
Wickham Place widened. Work will then move to
the main A4 Dublin Road on 9 January and work
will take place to widen 300 metres of Dublin
Road, as outlined in the description at the top
of this page. This work is due to be completed
by the end of March 2017. The total cost is
given as £500,000 which is a bit less than
predicted last year. Although only about 300m
long, the scheme has the potential to make a big
difference to the performance of this stretch of
the A4 through Enniskillen. This will see the
first phase of the longer-term "Wellington
Road Improvement Strategy" completed.
6 Apr 2016: I have decided
to create a page for this family of three
schemes now that it looks as if it could end up
being quite significant, if all three phases
outlined above go ahead. It needs to be stressed
that at this point in time only Phase 1 seems to
be progressing. The remaining two elements are
really aspirations. Planning for Phase 1
is well advanced. The DRD Minister spoke about it
in the Assembly around a year ago at which
point he stated that he had given the project
the go-ahead. As a result, the draft Vesting
Order (whereby the DRD buy the land needed) was
put
out to consultation over Christmas time,
ending on 4 January 2016. Following the
Consultation, the Fermanagh
Herald quoted the DRD as saying that "Plans
for a proposed road widening scheme in
Enniskillen at the A4 Dublin Road, between
Tempo Link road and the Wickham Link Road were
subject to public consultation on lands
acquisition in December and TransportNI is
currently considering the responses"
adding that "construction would be
likely to take around 16 weeks to complete".
As yet there does not seem to be a definite
timescale for construction. Planning for Phase
2 and Phase 3 seems to have been
underway since
at least 2012, but as yet have not
progressed towards construction.
|