Status
|
Construction scheme
(completed) |
Contractor
|
Gibson (Banbridge)
Ltd, with traffic signal work by Siemens
|
Where
|
To
widen Northway, Portadown, from 2+1
lanes to 2+2 lanes single-carriageway
standard from Seagoe to Kernan Loop. |
Total
Length
|
1.9 km / 1.2 miles
|
Dates
|
A3 Northway built
early 1970s as half of a future motorway
connecting Portadown and Lurgan.
c2011/12 - Section
from Edenderry to Seagoe widened to 2+2
lanes
28 Jan 2014 - Advance works contract
begins, to last 8 weeks
Early August 2014 - Main contract began,
due to last 16 weeks
24 Oct 2014 - Works
completed (5 weeks ahead of schedule)
New street lighting completed during
November
|
Cost
|
£1.5m
|
See
Also
|
General
area map - Google Maps
|
When it was decided
1965 to build a new city, Craigavon, by
connecting Portadown and Lurgan it was planned
that the two towns would be joined by two new
motorways - a Northway, to the north, and a
Southway, to the south. Initially the Northway
was to be built, and work began by constructing
the westbound carriageway only, whcih would
carry all traffic until such times as the growth
of the city meant that provision of a separate
northbound carriageway was required. By the
early 1970s the westbound carriageway of
Northway had been built from the Armagh Road
west of Portadown, through the town and half way
to Lurgan, but as the city plan stalled work
ground to a halt and nothing more was ever built
of Northway, leaving ghost
bridges over nothing and weird,
half-finished motorway junctions such as the M12
interchange here
and the planned city centre interchange here.
The map below shows the section of Northway that
exists today (in red and blue), which is
nevertheless a vital road, connecting the M1
motorway via the M12 to Portadown and hence on
to Armagh.
View A3
Northway as of Feb 2014 in a larger map
From Portadown to the
M12 junction (known as "Kernan Loop") Northway
is currently two lanes westbound (towards
Armagh) but only one lane eastbound (towards
Craigavon centre) which leads to bottlenecks and
congestion, especially in the morning peak (in
2014 the road was carrying 27,000 vehicles per
day). This arrangement was not original, but has
been achieved 'on the cheap' at some point in
the past couple of decades by repainting
slightly narrower lanes in order to increase
their number from 2 to 3. However this process
can't be repeated to create four lanes as the
resulting lanes would be much too narrow.
So this scheme will see
the 1.9km stretch from the Seagoe
Road signalised junction to Kernan Loop
widened to give two lanes each way. This stretch
is highlighted in RED on the map above. A short
adjacent stretch from Seagoe to the Shillington
river bridge was widened to 2+2 lanes round
2011/12. This is not the totality of the
remaining 2+1 stretches, but it is an important
chunk of it and the location of the scheme will
help traffic at Kernan Loop since where the
majority of traffic leaves Northway to get to
the M1. With thanks to Andrew Gallagher for
corrections to this.
Updates
31 Oct 2014: The scheme was
"substantially completed" last week according to
a press
release by DRD on 24 October. This is
about a month ahead of the expected completion
date of mid November, so represents excellent
progress by all involved. The main outstanding
task is the new street lighting which will take
place over the next couple of weeks, and the
30mph speed limit will remain until that is
done. The DRD Minister said "I congratulate
all those involved and would particularly
thank the public for their patience during the
works. This is a significant investment in
roads infrastructure which will bring benefit
to the many motorists using this vital link
between Armagh, Craigavon and Belfast."
25 Aug 2014: A site visitor (who prefers
to remain anonymous, but thank you) kindly sent
the below pictures which were taken last week
and show work underway. As you can see from the
first picture, all traffic is now using a
contra-flow on what was the southbound side of
the road, leaving the northbound lane for use by
the contractor. Picture 2 shows how work is
already underway to excavate the verge of the
road ready to extend the road base onto it to
provide the fourth traffic lane. More
legislation has appeared in connection with the
scheme - this
one bans overtaking on both this
stretch and the stretches to either side from 25
August to 16 November, which is pretty much the
time period anticipated for this project. This
one imposes a 30mph speed limit on the
stretch of Northway from Mill Avenue Portadown
to Asda Link Road Portadown. I can't quite see
the reasoning for this latter one, as it does
not cover the stretch of road being upgraded,
but its purpose may merely be to extend the
limits of this
one, which was passed a few weeks ago and
covers the stretch in question.
Pic 1: View north-east along Northway circa 20
August 2014, with all traffic using a
contra-flow on the right while the contractor
has use of the lane on the left. Work is already
underway on the far verge. [Anonymous site
visitor]
Pic 2: A few hundred metres further on from the
previous picture, and contractor's machinery has
clearly been at work excavating the bank here to
allow construction of the widened road base.
Circa 20 August 2014. [Anonymous site visitor]
16 Aug 2014: The DRD Minister confirmed
four days ago that this scheme has now begun. In
the previous update I noted that the temporary
speed limit was technically in force from 28
July, but since I haven't been in Portadown in
the intervening period I can't say exactly when
work actually began between then and 12 August.
However, the press release confirms that work is
due to be finished "before the end of the year".
The legislation providing for the temporary
30mph speed limit expires on 17 November 2014.
The photo below is the official one released by
the DRD showing representatives of both the
contractor and the DRD. It was taken on
the Seagoe Road flyover looking north-east
along part of the Northway that will be widened
from 3 to 4 lanes.
Left to right: Philip Greaves Contract Manager
(Gibson Brothers Limited); David McCaw Transport
NI Project Manager; Danny Kennedy Transport
Minister; and John Gibson Director Gibson
Brothers Limited. 12 August 2014. [DRD]
25 Jul 2014: Roads Service (or
TransportNI as they are now called) have released
a document imposing a temporary 30mph
speed limit on 3.5km of the north-eastbound A3
Northway from Asda Link Road to Highfield
Heights from 28 July 2014 for 16 weeks, ie until
roughly late November. This in itself
is unusual as it's not common to apply a
temporary speed limit in only one direction of
a single-carriageway road. (I was
wrong - speed limit applies in both
directions.) However it is very likely to
be to facilitate this widening scheme, and the
extent of the closure suggests that the majority
of widening works will take place on the
north-western side of the road. This coincides
nicely with the appointment
of the contractor Gibson (Banbridge) Ltd on 10
July. The 16 week timescale is slightly longer
than the 14 weeks estimated in the tender
document, but in practice this may just be to
provide resilience in the event of unforeseen
delays. This would mean completion in late
November 2014.
10 Feb 2014: In a press
release last week, the Minister announced
that this scheme, hitherto not publicised, would
be going ahead. It was apparently so secret that
it wasn't even mentioned in the most recent
report to Craigavon Borough Council last autumn!
He said that work has now begun (on 28 January)
on an advance contract to relocate street
lighting, drainage and crash barriers, along
with removal of vegetation and should last about
8 weeks, ie until late March. There will then be
a pause while the main contract will begin
"during the summer" and take about 14 weeks to
complete, so presumably in the autumn of 2014.
|