Status
|
Construction scheme
(completed) |
Contractor
|
?
|
Where
|
To
realign the B178 Hillsborough Road where
it meets the A23 near Moneyreagh.
Known locally as "Ewarts".
|
Total
Length
|
350 metres
|
Dates
|
14 Sep 2016 -
planning permission granted (ref
LA05/2015/0844/F)
September 2016 - work began
c6 Jun 2018 - road opened to traffic and
old Hillsborough Road closed off
|
Cost
|
£unknown - being
funded by a private developer
|
See
Also
|
General
area map - Google Maps
|
Click
here to jump straight down to updates
for this scheme.
The A23 connects Belfast to Ballygowan and on
to Saintfield. Although generally a good,
straight road is is punctuated by a series of
very busy staggered cross-roads that have been a
safety issue for many years, not to mention a
delay to traffic. One such junction is the B178/A23
junction at Moneyreagh, known to many as
the site of the former Ewarts stores. Attempts
to replace it with a roundabout in the past have
stalled due to high land costs. This scheme,
being carried out by a private housing
developer, will see the Hillsborough Road
realigned to the north as part of a 71-unit
development. The new stretch of road will be
about 350 metres long and it wil meet the A23
about 100 metres further north than at present.
This is shown on the design below, which is from
the Planning Service web site.
The realigned road will, oddly, convert the
junction into one that requires a right-left
movement to go straight on, rather than a
left-right movement, which is actually more
difficult for road users. However, in its
defence, it will split the two T-junctions much
further apart, and add a right-turn filter lane
on the new junction, which will reduce conflicts
between the two junctions. It will also allow
the possiility of a roundabout to be added at a
future date, since the B178 to the east has no
development at this point. It remains to be seen
how it will work in practice since sometimes
improving visibility and reducing conflicts can
actually encourage higher vehicle speeds. This
is one I can report on personally since I drive
through it several times a week.
The picture below shows the situation before
work began - this is looking north along the A23
Ballygowan Road (towards Belfast) with
Hillsborough Road to the left. It will be
diverted to emerge about 100 metres further
ahead.
View north along the A23 Ballygowan Road
(towards Belfast) with Hillsborough Road to the
left showing how the junction looked before work
began, circa 2015 [Wesley Johnston].
With many thanks to Alan Mannis for letting me
know about this scheme.
Updates
14 June 2018: The road was finally
completed and opened to traffic without ceremony
on or around 6 June 2018, following a lane
closure to complete the tie-in to the existing
road. I (naturally) went down a couple of days
later to tour the new link and I include six
photographs below. Although only 350 metres long
the new road has been completed to a high
standard with a 40mph design speed. Access to
the original alignment of the Hillsborough Road
from the main A23 has now been permanently
closed off with kerbing and soil, although the
road itself remains in use as a cul-de-sac for
access to existing properties. The new road
means that for traffic crossing over the A23,
the junction has changed from a relatively
straightforward left-right manoeuvre to a more
complex right-left manoeuvre which will take
some getting used to. Some people have also
commented that they think traffic coming from
the Ballygowan direciton is approaching the
junction at a higher speed now that there are no
longer people tryign to cross over from one side
to the other. My instinct is that DFI Roads want
to eventually realign the other arm of
Hillsborough Road and replace the newly finished
T-junction with a roundabout. I would give it
perhaps five years before we can expect to see
something along those lines happening! The
photos below are arranged in order starting at
the eastern end, ie the junction with the A23
Ballygowan Road.
Pic 1: View south along the A23 (with Belfast
behind the camera) showing the new T-junction
open and in use on 8 June 2018. In the distance
you can just see the cones blocking the original
entrance to Hillsborough Road (where the van is
turning). [Wesley Johnston]
Pic 2: Moving a few metres forward and looking
actoss the A23 this is the view along the new
road link, showing its high spec, complete with
turn right filter lane, traffic island, two
lanes for emerging traffic, twin footpaths with
tactile paving, a pair of keep-left bollards,
street lighting and even its very own little
area of hatching! The road name is even in
place, showing that the realigned road is taking
the same name as the one it replaced. 8 June
2018 [Wesley Johnston]
Pic 3: Very high standard fencing is a feature
along both sides of the eastern part of the new
road link. A Twitter discussion concluded that
the horizontals are meant to break free on
impact, thus presenting less of a hazard to
errant vehicles. The posts, however, are very
firmly cemented into the ground! 8 June 2018.
[Wesley Johnston]
Pic 4: Walking about 250 metres along the road,
this is the view west towards where the road
rejoins the original line of Hillsborough Road
(just beyond the digger). The road to the left
is a new entrance into the bypassed stretch of
Hillsborough Road which will remain as a
cul-de-sac to provide access to properties. 8
June 2018. The road has central hatching along
this stretch, which is used to provide
right-turn pockets to this, and an access into a
future housing development, off frame to the
right. [Wesley Johnston]
Pic 5: Walking down the little link road showin
in Pic 4, this the view west along the original
line of Hillsborough Road on 8 June 2018 showing
how the realigned road now swings off. The JCB
is presumably in the process of constructing a
turning head. [Wesley Johnston]
Pic 6: Walking another 100 metres along
Hillsborough Road and then turning round, this
is the view back the way we came, east, on 8
June 2018 from where the new road rejoins the
old one. The old road is visible beyond the JCB.
This is almost the same view as the last image
on this page, below, which was taken in October
2016. [Wesley Johnston]
22 Mar 2018: Work on the road seemed to
stall during 2017, but in the past couple of
months there has been a bit more progress once
again. Work on widening the existing A23 at the
point the new road joins it has taken place, as
shown by the kerb lines in the photo below. In
addition, a consultation
is now underway into a piece of legislation that
is required to stop up the existing Hillsborough
Road junction which will be closed once the
realigned road is opened. It's not clear what
timescale the developer is working to, but the
consultation suggests some progress towards
completion of the realignment.
View south on the A23 showing the kerbs in place
for the realigned Hillsborough Road on 16 March
2018 [Wesley Johnston].
28 Oct 2016: A small update to bring you
three photos I took three days ago showing the
works as they are now. The map at the top of
this page may be of some use in orienting
yourself in these pictures.
View west along the new road across the A23
Ballygowan Road on 25 Oct 2016. The stone base
layer seems to be in place but kerbing is yet to
go in. Some drainage works are probably also
underway at either side. [Wesley Johnston]
Moving a few dozen metres north (to the right)
from the previous photo this shows the curve in
the realigned Hillsborough Road. Seen from the
A23 Ballygowan Road on 25 Oct 2016. [Wesley
Johnston]
View east along Hillsborough Road towards the
western end of the new road. This is the point
that the realigned road will swing left onto the
new route. The old road will remain in place for
local access. Presumably the telephone pole in
the foreground will have to be relocated at some
point soon. Seen on 25 Oct 2016. [Wesley
Johnston]
23 Oct 2016: Visible work got underway
on this scheme during September, almost
immediately after planning permission was granted,
and as of today most of the base course of
gravel on the route of the diverted Hillsborough
Road has been built. No work has yet taken place
on the tie-in to the main A23. There was little
or no advance publicity due to this being a
private scheme.
|